What is a DNO, and why does a company you have never heard of get a say in your solar?

Your electricity supplier sells you units. A completely different company owns the wires those units arrive on, and it is that company, not your supplier, that decides how much solar you can connect.

Updated 4 August 2026 · written by the Clearline guidance team

7 dated sources, listed in full below Independent guidance, written to inform rather than sell Figures recomputed at every update, never recycled
A National Grid substation with transmission pylon behind, under a heavy sky

Supplier and network operator are two different companies

The company on your bill buys electricity and sells it to you. It does not own a single metre of cable outside your house. That is the job of your Distribution Network Operator, or DNO, which owns and operates the regional cables and substations that carry electricity to homes in your area.

You do not choose your DNO and you cannot switch it. It is determined entirely by where you live. Great Britain has 14 licensed DNO areas, owned between six groups, and your postcode places you in exactly one of them.

You can switch supplier tomorrow. You will have the same DNO forever.

This is why the DNO conversation catches people out. Everything about the retail energy market is built on choice and switching, and then a monopoly network operator with no customer relationship gets the final word on your generation capacity.

How to find yours in under a minute

There are three routes, and any one of them will do.

A National Grid substation with transmission pylon behind, under a heavy sky
Distribution substations like this one are the DNO’s side of the connection your application describes. Photo: Bob Harvey, CC BY-SA 2.0, via Wikimedia Commons
  1. Use the Energy Networks Association postcode lookup tool, which returns your operator directly.
  2. Call 105, the free national number for power cuts and network enquiries, which routes you to your regional operator automatically.
  3. Read your MPAN. On the bottom line of the long reference number on your bill, the first two digits are your distributor identifier.

The MPAN trick

MPAN stands for Meter Point Administration Number. It is the long block of digits on your electricity bill, arranged in a grid. The bottom line starts with a two-digit distributor ID, and that ID maps to one of the 14 DNO areas. If you are on the phone to an installation team, this is the fastest way to answer the question.

What your DNO actually controls

One thing, essentially: what you are allowed to connect to the network, and under what process. Solar panels do not just draw electricity, they push it back, and the network was designed for flow in one direction. The DNO's job is to keep the local network stable as more generation appears on it.

G98 and G99 grid connection routes Two routes for connecting a home energy system to the grid. Route one is G98: the installer fits the system and then tells the network operator it is connected, and this is the route for smaller installations. Route two is G99: the installer applies to the network operator and waits for approval before any work starts, and this is the route for larger installations. Either way, the installer handles the paperwork. G98 and G99 grid connections Every system that can export power follows one of two routes. 1 G98: fit first, notify after Your installer fits the system, then tells the network operator it is connected. The route for smaller installations. or 2 G99: apply first, then fit Your installer applies to the network operator and waits for approval before any work starts. The route for larger installations. Your installer handles the network operator paperwork either way.
The two routes a home energy system can take to its network operator.
Your inverter capacityProcessWhat happens
3.68kW per phase or less, which is 16A per phaseG98Connect and notify. The system is fitted first and the form goes to the DNO within 28 days of commissioning
Above 3.68kW per phase, or above 11.04kW on three phaseG99Approval required before installation. Standard determination is roughly four to eight weeks

G98 and G99 threshold and process guidance, accessed August 2026. The threshold applies to inverter AC rating per phase, not to panel capacity.

Note what is being measured there. It is the inverter's AC rating, not how many panels you have, which is why a well-designed system often carries far more panel capacity than the inverter number suggests. That is covered in inverter sizing explained, and the two processes are compared in full in G98 versus G99.

What it does not control

  • Planning permission. That is your local authority, and it is a separate question entirely.
  • Your export tariff. That is your electricity supplier, and rates differ enormously between them. Our tariffs guide carries the current picture.
  • How many panels you fit. The DNO regulates connected generation capacity at the inverter, not the roof.
  • Who installs it. Installations are carried out by an MCS-certified installation team for your area, and the DNO has no say in who that is.
Electricity transmission pylons reflected in still water at golden hour
The distribution network your export flows into. The DNO’s job is keeping it balanced. Photo: Garry Knight, CC BY 2.0, via Wikimedia Commons

Does it ever say no?

Under G98 it effectively cannot. A properly completed G98 notification cannot be rejected, because the system sits below the threshold at which the DNO has discretion. Under G99 it can, and occasionally does, though outright refusal is not the usual outcome.

More common is a condition. The DNO may require network reinforcement, which in rare cases is paid for by the applicant. Where a G99 is refused, the options are to fund the upgrade, cap the inverter at 3.68kW using export limitation, decline the connection, or reapply later when the local network has changed. The application itself is free, although installers may charge an administration fee for handling it.

Do you have to deal with any of this?

No. In a standard installation the homeowner files nothing. The installer handles G98 and G99 end to end, from application through to the commissioning paperwork, and the first most people hear of their DNO is when someone explains why the inverter is 3.68kW.

The reason it is worth understanding anyway is timing. A G99 adds weeks to a project, and knowing that up front lets you plan around it rather than discover it. Our solar panels guide sets out the full sequence from first call to commissioning.

Not sure which process your system needs? A free design call will size the inverter, name the process and give you a realistic timeline before you commit to anything.

Get your free quote

Regional differences are real

Fourteen operators means fourteen sets of internal processes, workloads and local network conditions. Determination times, appetite for larger connections and how quickly reinforcement gets flagged all vary between areas, which is one reason a national average timeline is only ever a guide.

Every county page on this site carries a calculator built for that area, so you can model a system against local conditions before you speak to anyone. Start at your county page, and if a term on your quote still does not make sense, our help centre works through the common ones.

FAQs

DNOs, answered

What does DNO stand for?

Distribution Network Operator. It is the company that owns and operates the regional cables and substations carrying electricity to homes in your area. Great Britain has 14 licensed DNO areas owned between six groups.

Who is my DNO?

It is set by where you live, not by choice. Find yours using the Energy Networks Association postcode tool, by calling 105, or by reading the first two digits of the bottom line of the MPAN on your electricity bill. All three routes give the same answer.

Is my DNO the same as my energy supplier?

No, and they are usually completely different companies. Your supplier buys and sells you electricity and you can switch it whenever you like. Your DNO owns the physical network, cannot be switched, and is the body that regulates what generation you can connect.

Can my DNO refuse my solar installation?

Under G98, a properly completed notification cannot be rejected, because the system sits below the threshold at which the DNO has discretion. Under G99 it can impose conditions or, occasionally, refuse. In that case the options are to fund network reinforcement, cap the inverter at 3.68kW, decline the connection, or reapply later.

Do I have to contact my DNO myself?

Not for a standard installation. The installer handles the G98 notification or the G99 application from start to finish, including the commissioning paperwork. It is worth knowing which process applies purely because a G99 adds weeks to the project timeline.

Does it cost anything to apply?

The application itself is free, though installers may charge an administration fee for preparing and submitting it. In rare cases a G99 outcome requires paid network reinforcement, which is a separate and potentially significant cost. That risk is one of the things worth establishing early on a larger system.

Figures and specifications in this guide are sourced below and were checked on the date shown. Rates and product specifications change; we confirm the current picture on your free design call.

Sources
  • What a DNO is and how to find yours, including the 105 number ovoenergy.com
  • Fourteen licensed DNO areas in Great Britain owned by six groups en.wikipedia.org
  • Finding your DNO by postcode and via the MPAN distributor identifier uw.co.uk
  • G98 connect and notify: threshold, 28 day submission, cannot be rejected when properly completed sunsave.energy
  • G99: prior approval, four to eight week standard determination, free application, refusal options including export limitation sunsave.energy
  • The threshold governs inverter AC rating per phase, not panel kWp sunsave.energy
  • Three phase connect and notify limit of 11.04kW blog.spiritenergy.co.uk
Free, no obligation

Get your free quote

Takes about two minutes. We work out your options, then confirm your free remote design call, on video, at a time that suits you. It starts with your roof and your numbers, and the design is built around them rather than around a product someone needs to shift.

Installations can only go ahead for homeowners, as the system is fixed to the property. Do carry on if you own it, or you are about to.
Flats and apartments usually share a roof, which rules most installations out. Send your details anyway and we will tell you honestly what is possible.
1 Where is your home?
Please add your full postcode
Please add your house number
2 About you
Please add your first name
Please add your last name
Please add a UK number
Please add a valid email
3 Your property
Do you own your home?
Please let us know
Property type
Please choose your property type
4 What are you after?
Please pick one, "not sure" is fine
Roughly is fine
Please choose a timeframe
5 When shall we call?
Best time for you (optional, but it helps)

We never call after 8pm.

Call 07782 219224

Free, no obligation. No home visit needed.

By submitting you agree we can contact you about your enquiry. We never sell your details and never pass them to a panel of installation teams. See our privacy notice.