HomeGuides › G98 vs G99: the 28-day form and the eight-week wait, in plain English

Solar

G98 vs G99: the 28-day form and the eight-week wait, in plain English

Two connection standards decide whether your solar install is a formality or a four to eight week wait. The dividing line is one number on your quote, and it is not the number most people expect.

Updated 4 August 2026 · written by the Clearline guidance team

7 dated sources, listed in full below Independent guidance, written to inform rather than sell Figures recomputed at every update, never recycled
A National Grid substation with transmission pylon behind, under a heavy sky

The dividing line

G98 applies when inverter capacity is 3.68kW per phase or less, which is 16A per phase. G99 applies above that, which on a three phase supply means above 11.04kW. Everything else follows from which side of that line your system sits on.

G98 and G99 grid connection routes Two routes for connecting a home energy system to the grid. Route one is G98: the installer fits the system and then tells the network operator it is connected, and this is the route for smaller installations. Route two is G99: the installer applies to the network operator and waits for approval before any work starts, and this is the route for larger installations. Either way, the installer handles the paperwork. G98 and G99 grid connections Every system that can export power follows one of two routes. 1 G98: fit first, notify after Your installer fits the system, then tells the network operator it is connected. The route for smaller installations. or 2 G99: apply first, then fit Your installer applies to the network operator and waits for approval before any work starts. The route for larger installations. Your installer handles the network operator paperwork either way.
Which route applies depends on size, and your installation team files the paperwork either way.

The number being measured is the inverter's AC rating, not the panel capacity on the roof. You can hang well over 4kWp of panels on a 3.68kW inverter and stay firmly within G98. That is not a loophole, it is how UK residential solar is routinely designed, and we explain the engineering behind it in inverter sizing explained.

Panels do not count. The inverter does.

Homeowners are regularly told there is a four panel or a ten panel limit. There is no such thing. The connection standard regulates how much AC power your system can push into the network at once, which is set by the inverter, and the panels above that rating simply extend your generating day.

G98: fit first, tell them after

G98 is a connect-and-notify process. The installer fits the system, commissions it, and then submits the G98 form to your Distribution Network Operator within 28 days of commissioning. No waiting, no approval stage, no risk of the project stalling.

A National Grid substation with transmission pylon behind, under a heavy sky
Distribution substations like this one are the DNO’s side of the connection your application describes. Photo: Bob Harvey, CC BY-SA 2.0, via Wikimedia Commons

The important detail is that a properly completed G98 notification cannot be rejected. Below the threshold, the DNO does not have discretion over whether you connect. This is why the standard UK single phase design has settled around 3.68kW of inverter with a fuller roof of panels behind it.

G99: ask first, wait, then fit

Above the threshold, the process reverses. The installer submits a G99 application and the DNO makes a determination before any installation work happens. A standard determination takes roughly four to eight weeks. Fast-track routes run at around two weeks, and complex cases can stretch to twelve.

The application itself is free, although installers may charge an administration fee for preparing and submitting it. In rare cases the DNO can require paid network reinforcement, which is a genuine cost risk worth establishing early on a large system.

G98G99
Applies whenInverter is 3.68kW per phase or less, which is 16A per phaseInverter is above 3.68kW per phase, or above 11.04kW on three phase
Order of eventsFit, commission, then notifyApply, wait for a determination, then fit
TimescaleForm submitted within 28 days of commissioningRoughly four to eight weeks standard, around two weeks fast-track, up to twelve for complex cases
Can it be refused?No, not when properly completedYes, or approved with conditions
CostFree application, installer may charge an admin feeFree application, installer may charge an admin fee, plus possible network reinforcement in rare cases
Who files itThe installerThe installer

G98 and G99 process and threshold guidance, accessed August 2026.

If a G99 is refused

Refusal is not the usual outcome, but it happens, and there are four routes from there.

Electricity transmission pylons reflected in still water at golden hour
The distribution network your export flows into. The DNO’s job is keeping it balanced. Photo: Garry Knight, CC BY 2.0, via Wikimedia Commons
  • Fund the network upgrade. Viable when the reinforcement cost is modest relative to the system.
  • Cap the inverter at 3.68kW. Export limitation brings the system back under the G98 threshold. You keep the panels and the self-consumption; you limit what flows out.
  • Decline the connection. Rare, and usually a signal to redesign rather than abandon.
  • Reapply later. Local network conditions change as reinforcement projects complete elsewhere.

Export limitation is not the disaster it sounds like

Capping the inverter limits what you can push to the grid, not what your panels generate or what your house can use. Given that self-consumed electricity is worth the rate you avoid paying and exported electricity is worth your export tariff, a cap costs you the difference on the exported units only. Our tariffs guide covers what those rates currently are.

Which one will apply to you

Start with your supply type. Most UK homes are single phase, where the ceiling is 3.68kW. If you have three phase, the same rule applies per phase and the ceiling is 11.04kW, which puts most residential systems comfortably inside G98. Our single phase versus three phase guide covers the sixty-second check at your fuse board.

Step 1

Check your supply

One cut-out fuse and two wires is single phase. Three 100A fuses and four wires, or L1 L2 L3 on the meter, is three phase.

Step 2

Find the inverter rating on your quote

It is a kW figure, separate from the panel kWp. On single phase quotes it is very often 3.68kW precisely because of this threshold.

Step 3

Compare the two

At or under 3.68kW per phase, you are in G98 territory and the timeline is unaffected. Above it, budget four to eight weeks before installation.

Step 4

Ask about reinforcement risk

Only relevant on a G99. It is rare, but it is the one outcome that carries a potentially significant unbudgeted cost.

You will not be filling in either form

In a standard installation carried out by an MCS-certified installation team for your area, the homeowner never files any of this. The installation team handles G98 and G99 end to end. What you should get is a clear answer on which process applies, and if it is G99, a realistic date rather than an optimistic one.

That paperwork also matters afterwards. Some suppliers require proof of grid connection from the DNO before they will pay you for exported electricity, alongside your MCS certificate and a smart meter capable of half-hourly export readings. Getting the connection documentation right is part of getting paid.

A free design call will tell you which process your system falls under, how long it realistically takes, and whether a slightly smaller inverter would save you two months.

Get your free quote

Every county page on this site carries a calculator for that area, so you can test different inverter sizes against your own usage before committing. Start at your county page, or read what a DNO is for the background on who is making these decisions.

FAQs

G98 and G99, answered

What is the difference between G98 and G99?

G98 is a connect-and-notify process for systems with an inverter of 3.68kW per phase or less, where the installation happens first and the form is submitted within 28 days of commissioning. G99 applies above that threshold and requires the network operator's approval before any installation work begins. The dividing line is the inverter's AC rating per phase.

How long does a G99 application take?

A standard determination takes roughly four to eight weeks. Fast-track routes run at around two weeks, and complex cases can stretch to twelve. Timescales vary between the 14 network operator areas, so treat any national figure as a guide rather than a promise.

Can I install more than 3.68kW of solar?

Yes. The 3.68kW threshold applies to the inverter's AC output per phase, not to panel capacity, so a system with well over 4kWp of panels can sit within G98. If you want inverter capacity above the threshold, that is a G99 application rather than a prohibition.

Does a G98 or G99 application cost anything?

The application itself is free, though installers may charge an administration fee for handling it. On a G99, the network operator can in rare cases require paid network reinforcement, which is a separate and potentially significant cost. That risk should be raised before you sign anything on a large system.

What happens if my G99 is refused?

There are four routes: fund the network upgrade, cap the inverter at 3.68kW using export limitation, decline the connection, or reapply later when local network conditions have changed. Capping the inverter is the most common practical answer, and it limits what you export rather than what your home can use.

Do I need to fill in the form myself?

No. In a standard installation the installer handles both processes end to end, from application to commissioning paperwork. What you should ask for is confirmation of which process applies and, on a G99, a realistic installation date.

Do I need the connection paperwork to get paid for exports?

Some suppliers require proof of grid connection from your network operator before enrolling you on an export tariff, alongside MCS certification and a smart meter that records export every 30 minutes. Keeping the commissioning documentation is worth doing properly. It is what unlocks the payments.

Figures and specifications in this guide are sourced below and were checked on the date shown. Rates and product specifications change; we confirm the current picture on your free design call.

Sources
  • G98 application: 3.68kW per phase threshold, 16A per phase, 28 day submission after commissioning, cannot be rejected when properly completed, installer files it sunsave.energy
  • G99 application: prior approval, four to eight week standard determination, around two weeks fast-track, up to twelve weeks complex, free application, admin fees, reinforcement risk, refusal options sunsave.energy
  • The threshold governs inverter AC rating, not panel kWp sunsave.energy
  • Three phase connect and notify limit of 11.04kW blog.spiritenergy.co.uk
  • Single phase and three phase supply identification ukpowernetworks.co.uk
  • Supplier requirements for export payment including G98 or G99 proof of grid connection and half-hourly export metering britishgas.co.uk
  • Smart Export Guarantee scheme rules and metering requirements ofgem.gov.uk
Free, no obligation

Get your free quote

Takes about two minutes. We work out your options, then confirm your free remote design call, on video, at a time that suits you. It starts with your roof and your numbers, and the design is built around them rather than around a product someone needs to shift.

Installations can only go ahead for homeowners, as the system is fixed to the property. Do carry on if you own it, or you are about to.
Flats and apartments usually share a roof, which rules most installations out. Send your details anyway and we will tell you honestly what is possible.
1 Where is your home?
Please add your full postcode
Please add your house number
2 About you
Please add your first name
Please add your last name
Please add a UK number
Please add a valid email
3 Your property
Do you own your home?
Please let us know
Property type
Please choose your property type
4 What are you after?
Please pick one, "not sure" is fine
Roughly is fine
Please choose a timeframe
5 When shall we call?
Best time for you (optional, but it helps)

We never call after 8pm.

Call 07782 219224

Free, no obligation. No home visit needed.

By submitting you agree we can contact you about your enquiry. We never sell your details and never pass them to a panel of installation teams. See our privacy notice.